Two meteorological stations are first long-term infrastructure at proposed Amagla gold mine

2 minutes ago
3 min read
Canadian company projecting April 2030 completion date for environmental review and permitting process of its mine 20 miles north of Juneau

One of two meteorological monitoring stations at the site for the proposed New Amalga Gold Project. (Photo provided by Grande Portage Resources Ltd.)
One of two meteorological monitoring stations at the site for the proposed New Amalga Gold Project. (Photo provided by Grande Portage Resources Ltd.)

By Mark Sabbatini

Juneau Independent


Grande Portage Resources Ltd. now knows which way the wind is blowing at its planned New Amalga Gold Project.


Also the temperature, relative humidity, barometric pressure, solar radiation and ambient concentrations of airborne particulate matter. The Canadian mining company announced Wednesday it has completed two meteorological monitoring stations for its proposed gold mine near Herbert Glacier about 20 miles north of downtown Juneau — the first long-term infrastructure at the site.


"The stations represent an important component of the Company's environmental baseline monitoring program and will provide data necessary to inform engineering design, environmental assessments, and future applications for air quality permits from the Alaska Department of Environmental Conservation (ADEC)," a press release by the company notes. "These emplacements represent the first long-term infrastructure built for the project, intended to be utilized throughout the duration of the potential future mining operation."


Workers at a drilling site for the proposed New Amalga Gold Project during the 2026 field season. (Photo provided by Grande Portage Resources Ltd.)
Workers at a drilling site for the proposed New Amalga Gold Project during the 2026 field season. (Photo provided by Grande Portage Resources Ltd.)

The announcement comes about a month after Grande Portage provided an update about its 2026 field season at the site that included completing 12 drillholes at five sites, five groundwater monitoring wells, and surveys for biological, geotechnical, cultural resource, floodplain and other purposes.


The company is projecting an April 2030 completion date for environmental review and permitting of the mine, according to the federal government’s FAST-41 Dashboard. The project was authorized for the expedited review process earlier this year.


Company officials have said the project is expected to create 277 jobs and a pre-tax net present value of nearly $1 billion during an initial seven-year production cycle. City Manager Katie Koester, during a Juneau Assembly retreat on Saturday, highlighted the mine as well as Goldbelt Inc.’s proposed private cruise dock on Douglas Island in noting "there are some really big projects that have really significant implications for our community on the horizon."


Opposition has been expressed by some people and organzations concerned about environmental impacts and disruption of recreational activities in the area. Also being questioned is if the state is subsidizing the project with its proposed Cascade Point Ferry Terminal, which includes road and other work the company will be able to use for an ore shipping site at the same location.


A worker laying out biological survey transect lines at a potential future barge dock site for ore from the proposed New Amalga Gold Project. (Photo provided by Grande Portage Resources Ltd.)
A worker laying out biological survey transect lines at a potential future barge dock site for ore from the proposed New Amalga Gold Project. (Photo provided by Grande Portage Resources Ltd.)

Grande Portage, in its announcement this week, stated the monitoring capabilities of the meteorological stations "are particularly important inputs for evaluating the dispersion of airborne particulates and informing the design of appropriate dust mitigation and environmental control measures for a future mining operation."


"The collected data will support the preparation of future ADEC air quality permit applications and provide an ongoing record of environmental conditions against which conditions during future construction and operations can be evaluated," the release states.


The company also noted it used several Juneau- and Alaska-based contractors for work that included "site preparation, foundation construction, tower engineering, helicopter logistics and project management."


• Contact Mark Sabbatini at editor@juneauindependent.com or 907-957-2306.


A helicopter transports a portion of a meteorological tower superstructure to the New Amalga Gold Project site during the 2026 field season. (Photo provided by Grande Portage Resources Ltd.)
A helicopter transports a portion of a meteorological tower superstructure to the New Amalga Gold Project site during the 2026 field season. (Photo provided by Grande Portage Resources Ltd.)

Cedar Clinic Ad 1.png
25HEC053_Radia_Ad_Graphic-Chelsea-300x25
rainbowfoodsad1.png
BFM Digital Ad-1.png
Ramada Ad PDF 7-10-26.png
CBJ Public Notice Web Tile 8.07.2026.png
Trust land office.jpg
Oct.14.png
JPM 2.png
Holiday Cheer (5).jpg
girl yeti spaceship juneau independent ad 2.jpeg
2027 LyndenAd-JI-300x250.jpg
bottom of page